Phase One Timeline

project image

  1. Book Inventory:  March 11 to May 17
    1. Inventory conducted by Backstage Library Works team (BSLW)
    2. Updating Library item information in Primo & Alma
  2. Book Move Preparation:  May 9 to May 24
    1.  Library Staff and BSLW tagging serial items on 2nd/ 3rd Floors
  3. Book Move:  May 20 to July 31
    1. BSLW will box items to move to new Library Annex
    2. BSLW will shift remaining items from 2nd/4th Floor Stacks to 3rd Floor Stacks & Basement compact shelving
  4. Library Annex Located at Nopper 910:
    1. New offsite annex for library Items
    2. Install Compact Shelving:  April 28 – July 8
  5. Library Lighting:
    1. Lighting will be updated througout the library. Details are being determined and will be posted here when available.
  6. Testing Center Expansion & Renovation:   May 20 to July 31
    1. Expansion of the testing center area
  7. Library 2nd / 4th Floor Renovation:  June 17 – August 16
    1. Removing stacks on 2nd / 4th Floors
    2. Paint & install new carpeting
    3. Install more patron work stations / study areas
    4. Implement Researcher Services space
  8. Library Staff Room 134 Renovation:  June 24 to September 17
    1. Expansion and renovate librarian faculty, cataloging, ILL, and DLI staff areas

For additional information contact:

Montana State University Library 
406-994-3119